We found the notice clause after the window closed.

Notice and submittal obligations each start on a trigger. The trigger is written somewhere in hundreds of pages nobody has time to re-read, and the window closes whether anyone saw it or not.

Which clocks are running on this job right now?

Scope and fee agreed up front. No implementation. NDA first.
Notice triggers — A201-1997 §4.3
Trigger → window
§4.3.2Time limits on claims
21 days
Starts: The event, or when you first recognise it
§4.3.4Concealed or unknown conditions
Before disturbed, 21 days at most
Starts: First observance of the condition
§4.3.5Claims for additional cost
Before you start
Starts: Before proceeding with the work
§4.3.7Claims for additional time
21 days, per §4.3.2
Starts: The delay event

The windows as the standard form writes them. Supplementary conditions often change them, and that is what the review checks.

Why it gets missed

Nobody misses a notice on purpose.

01
The trigger is an event, not a date

Nobody diarises a clause. The clock starts when something happens on site, and the person who sees it is rarely the person who read the contract.

02
The clause sits in a document nobody re-reads

General conditions, supplementary conditions, the agreement, Division 01. Notice provisions are spread across all of them.

03
The package changed the standard window

Your team knows 21 days from the form. Supplementary conditions can shorten it, and nobody compares the two.

The records involved

Notice provisions live in more places than anyone checks.

The agreementGeneral conditionsSupplementary conditionsDivision 01 general requirementsSpecification sectionsAddenda and bulletinsSubcontract flow-downs
What good looks like

Every clock known before it starts.

10 days
Claim notice, DFW Data Center 1 §50-17
5 days
Claim update once the work is done

In one real bid package, each cited to document, section and page.

01
Every notice obligation, with its trigger

What starts each clock, cited to the clause and page, before the event happens.

02
Who gives notice, and to whom

Including the obligations the contract never assigns to a party.

03
The window as your package writes it

Not the one your team remembers from the standard form.

04
What would prove notice was given

The acceptance test, so the record answers the question before anyone asks it.

A notice clock is running

Show us the job
where the clock is running.

Bring the executed contract and the package. We return every notice and submittal obligation, with the trigger and the window your package actually writes.

No implementation. Start with the records you already have.